Trafford Park, Manchester · industrial

A new main switchboard in a 72-hour shutdown

  • £300k to £400k
  • Distribution and containment
  • 12 weeks, around a 72-hour shutdown
  • Completed December 2025

The project

Download this case studyPDF, one page

Client
A food manufacturer
Main contractor
Direct for the manufacturer
Consultant
The manufacturer's engineering team
Location
Trafford Park
Contract value
£300k to £400k
Programme
12 weeks, around a 72-hour shutdown
Floor area
9,500 m² production hall
Form of contract
NEC4 Engineering and Construction Short Contract
Our role
Principal electrical contractor
Completed
December 2025
Occupied throughout
Yes: production ran right up to the shutdown
Safety
0 lost-time incidents

The result in numbers

  • 72 hoursthe whole changeover, inside the shutdown
  • 6 hoursahead of the planned restart
  • 0product lost to the works
  • 2000 Amain switchboard installed and commissioned
  • 180sealed LED high-bays to the hygiene standard
  • 0lost-time incidents

The brief

A food manufacturer in Trafford Park needed its main switchboard replaced, and could only be without power for one 72-hour window over Christmas.

What we worked around

  • The supply could be off for one 72-hour window over the Christmas shutdown, and no longer
  • Everything above the lines sealed and wipe-clean, to the site's hygiene rules
  • Permits to work and lock-off agreed each shift with the site's engineering team

Our solution

We moved everything we could out of the shutdown: the switchboard was built and tested off site, every new sub-main was run and terminated short of the board in the weeks before, and the changeover was rehearsed on paper with the site's engineers, shift by shift.

The shutdown: new switchboard beside the old, under lock-off

What we installed

  • A new 2000 A main switchboard, built off site and installed over the shutdown
  • New sub-mains on cable ladder to every production line
  • Sealed LED high-bays to the hygiene standard in the production hall
  • A thermographic survey of the new switchgear under load after the restart
Armoured cables into the new panel's gland plate

Programme

Twelve weeks of preparation around production, then the changeover in 72 hours over the Christmas shutdown, with a thermographic survey under load in January.

The result

Power was restored and the lines restarted six hours ahead of plan, with no product lost and no lost-time incident.

Handover

A single-line diagram as fitted, the switchboard's test results, the thermographic baseline under load and the O&M manual.

A B C D E F 1 2 3 4 RISER DB-A2 DB-B3 DB-C3 33.0 m N CONTAINMENTDISTRIBUTION BOARDFLOOR BOX A NEW MAIN SWITCHBOARD IN A 72-HOUR SHUT DRG MR-7945-E-220 ILLUSTRATIVE ONLY SCALE 1:200 REV C
Illustrative drawing generated for this record, not the client's building.

Six hours early on a shutdown we'd been dreading all year. The planning was the best we've seen.

Engineering manager, food manufacturer