Download this case studyPDF, one page
- Client
- A sixth-form college
- Main contractor
- A regional education contractor
- Consultant
- The college's M&E consultant
- Location
- Bolton
- Sector
- Education
- Contract value
- £200k to £300k
- Programme
- 7 weeks in the summer holiday
- Floor area
- 8 laboratories and 2 prep rooms
- Form of contract
- JCT Intermediate subcontract
- Our role
- Electrical subcontractor
- Completed
- August 2025
- Occupied throughout
- Empty for the summer, with a summer school next door
- Safety
- 0 lost-time incidents
The result in numbers
- 3 daysearly, before the staff training days
- 8laboratories rewired
- 416bench power and data outlets
- 10emergency isolation panels
- 0teaching days lost
The brief
A sixth-form college in Bolton was refurbishing its science block over the summer and needed eight laboratories and two prep rooms rewired before the staff came back.
What we worked around
- Seven weeks between the end of term and the staff training days, with no slack
- Shared with the college's refurbishment contractor and the fume cupboard installer
- Every operative DBS checked, because the college ran a summer school next door
Our solution
We wrote the programme with the refurbishment contractor and the fume cupboard installer before the holiday started, ran two teams so first fix finished ahead of the benches, and tested each lab's isolation panel and fume cupboard interlocks as soon as it was complete.

What we installed
- Bench power and data in eight laboratories and two prep rooms
- Emergency isolation panels with stop buttons in every laboratory
- LED lighting with daylight control, and emergency lighting
- Supplies to the new fume cupboards, interlocked with their extract

Programme
Seven weeks inside the summer holiday, with each laboratory tested and handed over in turn so the science staff could set up during the last week.
The result
Every laboratory was handed back three days early, with no teaching days lost.
Handover
Test certificates for each laboratory, the isolation panel functional test records, as-fitted drawings and the O&M manual, in the college's portal.
They planned around everyone else on site, which is why the whole job finished early.