Bolton · education

A science block rewired in one summer holiday

  • £200k to £300k
  • Commercial fit-out
  • 7 weeks in the summer holiday
  • Completed August 2025

The project

Download this case studyPDF, one page

Client
A sixth-form college
Main contractor
A regional education contractor
Consultant
The college's M&E consultant
Location
Bolton
Sector
Education
Contract value
£200k to £300k
Programme
7 weeks in the summer holiday
Floor area
8 laboratories and 2 prep rooms
Form of contract
JCT Intermediate subcontract
Our role
Electrical subcontractor
Completed
August 2025
Occupied throughout
Empty for the summer, with a summer school next door
Safety
0 lost-time incidents

The result in numbers

  • 3 daysearly, before the staff training days
  • 8laboratories rewired
  • 416bench power and data outlets
  • 10emergency isolation panels
  • 0teaching days lost

The brief

A sixth-form college in Bolton was refurbishing its science block over the summer and needed eight laboratories and two prep rooms rewired before the staff came back.

What we worked around

  • Seven weeks between the end of term and the staff training days, with no slack
  • Shared with the college's refurbishment contractor and the fume cupboard installer
  • Every operative DBS checked, because the college ran a summer school next door

Our solution

We wrote the programme with the refurbishment contractor and the fume cupboard installer before the holiday started, ran two teams so first fix finished ahead of the benches, and tested each lab's isolation panel and fume cupboard interlocks as soon as it was complete.

Summer: bench trunking going in, with our apprentice

What we installed

  • Bench power and data in eight laboratories and two prep rooms
  • Emergency isolation panels with stop buttons in every laboratory
  • LED lighting with daylight control, and emergency lighting
  • Supplies to the new fume cupboards, interlocked with their extract
A laboratory's emergency isolation panel by the door

Programme

Seven weeks inside the summer holiday, with each laboratory tested and handed over in turn so the science staff could set up during the last week.

The result

Every laboratory was handed back three days early, with no teaching days lost.

Handover

Test certificates for each laboratory, the isolation panel functional test records, as-fitted drawings and the O&M manual, in the college's portal.

A B C D E F 1 2 3 4 RISER DB-A3 DB-B1 44.0 m N CONTAINMENTDISTRIBUTION BOARDLUMINAIRE A SCIENCE BLOCK REWIRED IN ONE SUMMER HO DRG MR-5890-E-213 ILLUSTRATIVE ONLY SCALE 1:200 REV C
Illustrative drawing generated for this record, not the client's building.

They planned around everyone else on site, which is why the whole job finished early.

Estates manager, sixth-form college