Piccadilly, Manchester · hospitality

Seven guest floors rewired, one floor at a time

  • £250k to £350k
  • Commercial fit-out
  • 22 weeks
  • Completed January 2026

The project

Download this case studyPDF, one page

Client
A city-centre hotel operator
Main contractor
A hotel refurbishment contractor
Consultant
The operator's M&E consultant
Location
Manchester
Contract value
£250k to £350k
Programme
22 weeks
Floor area
140 bedrooms over seven floors
Form of contract
JCT Intermediate subcontract
Our role
Electrical subcontractor
Completed
January 2026
Occupied throughout
Yes: the hotel stayed open, with one floor closed at a time
Safety
0 lost-time incidents

The result in numbers

  • 140bedrooms rewired and relit
  • 7floors, each back on sale on its planned date
  • 0bookings cancelled because of the works
  • 0hours an occupied floor went without fire alarm cover
  • 52%lower corridor lighting energy

The brief

A hotel operator was refurbishing every guest floor of a city-centre hotel near Piccadilly. Its refurbishment contractor needed an electrical subcontractor who could work floor by floor without the guests noticing.

What we worked around

  • Only one floor out of use at a time, so the hotel kept selling the rest
  • Drilling and chasing only between 10am and 4pm, between check-out and check-in
  • Guest lifts never used for materials, only the service lift at booked times
  • The fire alarm kept live on every occupied floor while its devices were replaced

Our solution

Each floor was sealed behind a dust screen and handed to us for three weeks. Drilling and chasing ran between check-out and check-in, materials went up the service lift at booked times, and the fire alarm on the floors around us stayed live while the closed floor's devices were replaced.

During: a guest floor stripped back behind a dust screen

What we installed

  • New sub-mains and a distribution board on every guest floor
  • Bedroom power, USB outlets and bedside controls to the designer's layout
  • Corridor and bedroom lighting with presence detection in the corridors
  • Emergency lighting and fire alarm devices replaced to the new layout
The floor's new distribution board in its riser

Programme

Twenty-two weeks for seven floors, a floor every three weeks, with commissioning and the floor's own fire alarm cause-and-effect test before each one went back on sale.

The result

All seven floors went back on sale on their planned dates, with no booking cancelled because of the works and corridor lighting energy down by more than half.

Handover

As-fitted drawings, test certificates and the fire alarm cause-and-effect record for each floor, handed to the hotel's engineer as each floor reopened.

A B C D E F G 1 2 3 4 RISER DB-A1 DB-B3 DB-C3 50.0 m N CONTAINMENTDISTRIBUTION BOARDLUMINAIRE SEVEN GUEST FLOORS REWIRED, ONE FLOOR AT DRG MR-3985-E-214 ILLUSTRATIVE ONLY SCALE 1:200 REV C
Illustrative drawing generated for this record, not the client's building.

Every floor came back on the day they said, so we never had to cancel a booking.

General manager, city-centre hotel