Download this case studyPDF, one page
- Client
- A commercial landlord
- Main contractor
- A regional refurbishment contractor
- Consultant
- The landlord's building services engineer
- Location
- Altrincham
- Sector
- Offices and workplace
- Contract value
- £600k to £750k
- Programme
- 20 weeks
- Floor area
- 4,200 m² over four floors
- Form of contract
- JCT Design and Build subcontract
- Our role
- Electrical subcontractor, design and build
- Completed
- September 2025
- Occupied throughout
- Yes: two floors stayed let and trading
- Safety
- 0 lost-time incidents in 11,000 hours
The result in numbers
- 4floors refurbished to Cat A
- 0interruptions to the let floors' supply
- 12tenancies sub-metered
- 1 Sundayto change over the landlord's switch room
- 62%lower lighting energy on the refurbished floors
The brief
A commercial landlord was refurbishing four floors of a 1980s office building in Altrincham to Cat A, with two other floors still let and trading.
What we worked around
- Two floors still let and trading, with their supply kept on throughout
- The landlord's switch room changed over on a single Sunday
- The agent's marketing date fixed before work started
Our solution
We designed the new risers so every let floor could be moved onto them one at a time, built the landlord's new switchboard alongside the old one and changed over on a single Sunday. Every tenancy got its own sub-meter, so the landlord can recharge energy accurately.

What we installed
- A new landlord's main switchboard with sub-metering for every tenancy
- New risers and containment, and floor boxes in the raised floor
- LED lighting with presence and daylight control to Cat A standard
- Emergency lighting and fire alarm across the refurbished floors

Programme
Twenty weeks, with the switch room changeover on week nine and the floors handed over in pairs.
The result
The floors were ready on the agent's marketing date, the let floors never lost supply, and lighting energy on the refurbished floors fell by 62%.
Handover
As-fitted drawings, the sub-metering schedule, test certificates and the O&M manual, with a building log book for the landlord's managing agent.
We could market the floors with confidence because they were never going to miss the date.