Altrincham · offices

A Cat A refurbishment with two floors still let

  • £600k to £750k
  • Commercial fit-out
  • 20 weeks
  • Completed September 2025

The project

Download this case studyPDF, one page

Client
A commercial landlord
Main contractor
A regional refurbishment contractor
Consultant
The landlord's building services engineer
Location
Altrincham
Contract value
£600k to £750k
Programme
20 weeks
Floor area
4,200 m² over four floors
Form of contract
JCT Design and Build subcontract
Our role
Electrical subcontractor, design and build
Completed
September 2025
Occupied throughout
Yes: two floors stayed let and trading
Safety
0 lost-time incidents in 11,000 hours

The result in numbers

  • 4floors refurbished to Cat A
  • 0interruptions to the let floors' supply
  • 12tenancies sub-metered
  • 1 Sundayto change over the landlord's switch room
  • 62%lower lighting energy on the refurbished floors

The brief

A commercial landlord was refurbishing four floors of a 1980s office building in Altrincham to Cat A, with two other floors still let and trading.

What we worked around

  • Two floors still let and trading, with their supply kept on throughout
  • The landlord's switch room changed over on a single Sunday
  • The agent's marketing date fixed before work started

Our solution

We designed the new risers so every let floor could be moved onto them one at a time, built the landlord's new switchboard alongside the old one and changed over on a single Sunday. Every tenancy got its own sub-meter, so the landlord can recharge energy accurately.

An office floor mid-refurbishment before the ceilings went in, new containment and cable tray overhead and floor tiles lifted, Marlow & Reed's managing director pointing up at the containment as he walks the landlord's agent round.
During: walking the landlord's agent under the containment

What we installed

  • A new landlord's main switchboard with sub-metering for every tenancy
  • New risers and containment, and floor boxes in the raised floor
  • LED lighting with presence and daylight control to Cat A standard
  • Emergency lighting and fire alarm across the refurbished floors
The landlord's new switchboard and tenant sub-meters

Programme

Twenty weeks, with the switch room changeover on week nine and the floors handed over in pairs.

The result

The floors were ready on the agent's marketing date, the let floors never lost supply, and lighting energy on the refurbished floors fell by 62%.

Handover

As-fitted drawings, the sub-metering schedule, test certificates and the O&M manual, with a building log book for the landlord's managing agent.

A B C D E F 1 2 3 4 RISER DB-A3 DB-B3 DB-C1 40.0 m N CONTAINMENTDISTRIBUTION BOARDFLOOR BOX A CAT A REFURBISHMENT WITH TWO FLOORS ST DRG MR-4814-E-235 ILLUSTRATIVE ONLY SCALE 1:200 REV D
Illustrative drawing generated for this record, not the client's building.

We could market the floors with confidence because they were never going to miss the date.

Asset manager, commercial landlord